Why is an investment in the AEP storage project in Obernberg am Inn worthwhile?

AEP Obernberg combines an already operational solar park with a planned large-scale battery storage system at the same location. Existing energy generation with ongoing revenues thus meets additional marketing opportunities through flexible storage.

1

Existing Solar Park

The solar park with approximately 6 MWp is already in operation. The generated electricity is primarily marketed through the regional energy community.

Learn more
2

Large-scale storage with concrete project progress

6 MW of capacity and 12 MWh of storage capacity are planned. Commissioning is scheduled for Q2/2027; the grid connection approval for 5.5 MW has already been granted.

Learn more
3

Financing and implementation with established partners

Senior financing tranches totalling 6.64 million euros have been secured for the land, solar park and battery storage system. Specialised project partners are planned for construction, technology and marketing.

Learn more

Your investment is not protected by the deposit guarantee schemes established pursuant to Directive 2014/49/EU (Deposit Guarantee Schemes Directive). Your investment is also not protected by the investor compensation schemes established pursuant to Directive 97/9/EC (Investor Compensation Schemes Directive).

First name Last name, Position

“With AEP Obernberg, we are combining an already operational solar park with a flexible battery storage system. Our aim is to make regional renewable energy more usable while at the same time contributing to the stability of the power system. Our experience in building and operating solar installations provides a solid foundation for this. Invest today in the energy infrastructure of tomorrow and shape the energy transition with us."

Gerald Wirtl-Gutenbrunner, CEO

Investment information

Days to invest:
21
Investing round ends:
12/10/2026
Type:
Bond
Subordinated:
no
Invested so far:
€182,500.00
Price per bond:
€250.00
Transaction costs:
1.50 %
Min offer:
1 Unit
Maximum issue size:
€2,285,000
in 9,140 Units
Interest:
quarterly
Repayment:
quarterly
after 15 Months
ISIN:
DE000A4E0QJ3
Broker:
Oneplanetcrowd International B.V
License:
ECSPR

Overview

Project introduction: Solar park and battery storage system at a shared location

AEP Obernberg combines an existing solar park with a planned battery storage system at the same location in Obernberg am Inn, Upper Austria. The solar park has a capacity of approximately 6 MWp and is already in operation. In addition, a battery storage system with 6 MW and 12 MWh of storage capacity is planned. The land and solar park are owned by the project company AEP OBB GmbH.

The generated solar electricity is primarily marketed through the existing regional energy community. Quantities not absorbed there flow into other energy communities or the public grid.

The planned battery storage system can absorb electricity independently of the solar park's current production and release it again at a later point in time. This allows it to be deployed on various electricity markets and create additional marketing opportunities for the project. CyberGrid is intended to take over the marketing and optimisation of the storage system. Completion and commissioning are planned for the second quarter of 2027. Revenues from the battery storage system can only be generated after successful construction, grid connection and commissioning.

01 In operation

Solar park

Power production running

The solar park with approximately 6 MWp capacity has been built, connected to the grid and is in operation. The generated electricity is primarily marketed through the regional energy community.

Approx. 6 MWp capacity
02 In preparation

Battery storage

Commissioning planned for 2027

The battery storage system is currently in preparation. A grid connection approval of 5.5 MW has already been obtained for the planned grid connection.

6 MW capacity | 12 MWh storage capacity

Project milestones

  1. Achieved

    Solar park in operation

    Power production is already running.

  2. Achieved

    Electricity supply started

    The energy community is receiving solar electricity.

  3. In preparation

    Prepare financing

    The project financing is being implemented.

  4. Planned

    Build storage system

    Delivery, assembly and technical connection.

  5. Q2 2027

    Commission storage system

    Start of planned commercial marketing.

How are revenues generated?

AEP Obernberg combines two different revenue sources: existing income from electricity production and planned revenues from the marketing of the battery storage system.

1. Revenues from the solar park

The solar park already generates revenues from the sale of the electricity it produces. This is primarily supplied to the regional energy community. The currently agreed electricity price is 11 ct/kWh.

The actual revenues depend in particular on the amount of electricity generated, offtake within the energy community and the electricity prices agreed in each case.

2. Revenues from the battery storage system

After construction, grid connection and commissioning, the battery storage system is intended to generate additional revenues. This will include in particular participation in the balancing energy market and short-term electricity trading. In short-term electricity trading, the storage system can absorb electricity at low market prices and release it again at higher market prices. CyberGrid is to take over the marketing and ongoing optimisation. The revenues actually achievable depend, among other things, on market prices, technical availability, energy losses and marketing costs.

Would you like to learn more about battery storage systems?

Battery storage systems are playing an increasingly important role in an energy system with a growing share of renewable electricity generation. Find out how large-scale battery storage systems work, in which markets they operate and which factors influence their economic viability in the Invesdor blog. Read blog article

AEP H2 GmbH and management

AEP H2 GmbH develops and implements energy solutions for companies, municipalities and other project partners. Its range of services covers photovoltaic systems, battery storage, solar carports, charging infrastructure and energy communities. AEP supports projects from planning and financing through implementation to ongoing operation. To date, approximately 400 owned photovoltaic systems with a total capacity of around 40 MWp and battery storage systems with a total capacity of around 4 MWh have been realised. For the implementation of AEP Obernberg, AEP takes on project development and technical and commercial management. Specialised partners are engaged for specific areas of the project.

Gerald Wirtl Gutenbrunner

CEO

Gerald Wirtl-Gutenbrunner has many years of experience in the photovoltaic and energy sector and, as CEO, is responsible for the strategic direction of the entire company. The acquisition of major projects and a significant share of new project development also pass across his desk.

In the AEP Obernberg project, Gerald Wirtl-Gutenbrunner is responsible for strategic project assessment and due diligence. Together with the AEP team, he evaluates economic, technical and project-specific risks, thereby providing a key basis for investment and implementation decisions.

Mag. Dr. Thomas Eidenberger

CFO

Mag. Dr. Thomas Eidenberger is an experienced finance and capital markets expert. Through his many years of experience in managing local and international companies, he brings substantial expertise in the field of financing. Eidenberger also has many years in the photovoltaic industry behind him and is additionally a court-certified expert witness.

Corporate structure

AEP H2 GmbH develops and manages the AEP Obernberg project. AEP OBB GmbH is the project company for the site and the owner of the land as well as the existing solar park. The planned battery storage system is also intended to be realised at the level of AEP OBB GmbH.

Currently, AEP H2 GmbH holds 100% of the shares in AEP OBB GmbH. In the course of the financing, these shares are to be taken over by AEP2 FNZ GmbH, which in turn is 100% owned by AEP H2 GmbH.

Investors invest in the bond issued by AEP2 FNZ GmbH. The capital raised is passed on as a subordinated loan to AEP OBB GmbH and used there to refinance project funds already deployed as well as for the construction and commissioning of the battery storage system.

Investors do not acquire a direct participation with the bond an der AEP OBB GmbH.

Parent Company

AEP H2 GmbH

Mainly develops projects and acts as operator of AEP OBB GmbH
for commercial and technical management.

100% of shares

Intermediate Company

AEP2 FNZ GmbH

Manages the project and continues its development.

100% of shares Subordinated loan

Project Company

AEP OBB GmbH

Holds the property as well as the solar park and the planned
battery storage system.

Partners for financing, technology and implementation

For the implementation of AEP Obernberg, AEP works with partners for financing, construction, storage technology, grid connection and marketing. The overview shows their respective role in the project.

Project Partners and Their Roles

Partner Role Expertise and Project Contribution
AEP H2 GmbH Project development as well as technical and commercial management AEP is responsible for the development, implementation, and management of the project. The company has so far implemented around 250 rooftop PV systems with a total of around 10.5 MWp, as well as battery storage systems with a capacity of around 1.5 MWh.
AEP2 FNZ GmbH Management and further development of the AEP OBB GmbH project AEP2 FNZ GmbH is a 100% subsidiary of AEP H2 GmbH. It is the issuer of the bond offered via Invesdor and is intended to take over the shares in the project company AEP OBB GmbH.
AEP OBB GmbH Project company and owner of the project site AEP OBB GmbH holds the site and the existing solar park at the Obernberg location. The planned battery storage system is also to be implemented within this project company.
UniCredit Austria Senior financing partner Three senior financing tranches with a total volume of EUR 6.64 million have already been committed for the site, solar park, and battery storage system. The bank financing takes priority over the Invesdor bond in terms of repayment.
GTS Works GmbH Construction and technical implementation of the battery storage system GTS Works is AEP's implementation partner and has already been involved in existing projects, including the Obernberg and Ferschnitz solar parks. For AEP Obernberg, GTS Works is designated for the construction and technical implementation of the battery storage system.
Sungrow Battery and inverter technology Sungrow is designated as the technology partner for the battery and inverter technology of the planned battery storage system. Sungrow is among the world's leading BESS integrators and ranks number 1 worldwide in the current Wood Mackenzie ranking.
CyberGrid Marketing and optimization of storage capacity CyberGrid specializes in marketing flexible energy assets and will market the battery storage system on suitable electricity markets while continuously optimizing its operation. Since 2022, CyberGrid has been a 100% subsidiary of the EVN Group, Austria's largest grid operator.
Netz Oberösterreich Grid connection and grid-side requirements The solar park is already connected to the power grid. A grid connection commitment of 5.5 MW is in place for the battery storage system.
Regional Renewable Energy Community – Perspektive Energie Offtake of the solar power The solar power generated is used primarily within the regional energy community. The currently agreed electricity price is 11 ct/kWh net.

Sources & use of funds

According to the current budget planning, a total investment of 9.887 MEUR is planned for AEP Obernberg. This covers construction and infrastructure costs, development, advisory and transaction costs, construction-period interest and financial reserves.

The financing consists of equity, senior debt and the financing offered via Invesdor.

The table below shows the sources and use of funds of the project. 

Sources of Funds Use of Funds
Source Amount Share Use Amount Share
Bank FinancingLand, PV and BESS 6.64 million euros Land 1.889 million euros
Invesdor LoanAs subordinated loan 2.285 million euros BESS 2.508 million euros
Equity 962,036 euros PV System 4.8 million euros
Development Rights 690,036 euros
Total Sources of Funds 9.887 million euros Total Use of Funds 9.887 million euros

Cash flow & repayment of the bond

The planned payments to investors are made from the available cash flows of the project. These initially come from the ongoing operation of the solar park. Once the battery storage system has been completed and commissioned, additional revenues from its marketing will be added. The bond has a term of seven years and provides a fixed interest rate of 8.00 % p.a. as well as quarterly interest payments. The principal of the bond is to be repaid in stages from 2028 onwards over the remaining term.

Start
Start of term
30.09.2026
%
Interest payments
from 30.12.2026, quarterly
First redemption 
planned from 2028 
Full repayment
October 2033

Sustainability and SDGs

Contribution to the UN Sustainable Development Goals

Renewable energy and a more flexible electricity system

The solar park supports the regional use of renewable energy. The planned storage facility can provide additional flexibility by storing and releasing electricity at different times.

SDG 7: Affordable and clean energy
SDG 7
Affordable and clean energy
SDG 13: Mameasures for climate action
SDG 13
Climate change mitigation measures

Financial figures

Actual and projected figures

Get insight into the company's financial figures, such as the development of revenue and earnings. Find out more about the growth forecast.

Login Sign up

Collateral & Risks

Collateral

The following security is provided for this funding round: a guarantee from AEP H2 GmbH in the amount of 300,000 euros and the assignment by way of security of the rights and claims arising from the subordinated loan between AEP2 FNZ GmbH and AEP-OBB GmbH.

The value of the collateral may fluctuate, particularly in the event of a default, which may result in a lower return. Detailed information on the collateral can be found in the KIIS in the documents section for this funding round.

Risk summary (simplified)

Investments in growth companies through bonds involve a very high level of risk. You may lose part or all of the money you invest.

The following text provides a brief and highly simplified overview of selected risks associated with an investment in AEP2 FNZ GmbH.

It is not exhaustive and does not replace the detailed description of the risks contained in the Key Investment Information Sheet (KIIS).

Before investing, you must read the KIIS in full and carefully assess whether you understand and are able to bear all the risks described therein.

In the event of any discrepancies between this summary and the KIIS, only the KIIS shall be legally binding.

Key risk areas (brief overview)

Project implementation and operation: The battery storage facility is still under construction. Construction, delivery, installation, technical malfunctions, battery degradation and safety incidents may cause delays or additional costs. Important contracts have not yet been finalised; suppliers or service providers may fail to perform. This may reduce project revenues.

Energy market and regulation: Revenues from the PV system depend on the sale of electricity to an energy community. Prices are agreed annually; there are no long-term fixed offtake volumes. Revenues from the battery storage facility are based on forecasts in a still-developing market. Electricity prices, grid restrictions, charges, taxes and regulations may change.

Default and returns: Interest and repayment depend on AEP2 FNZ GmbH receiving payments from AEP OBB GmbH. The project’s bank financing has priority over the loan granted by AEP2 FNZ GmbH to AEP OBB GmbH. The collateral and guarantee may not cover all investor claims. If cash flow is insufficient or one of the companies becomes insolvent, payments may be delayed or may not be made at all; a total loss is possible. Inflation, costs and your individual tax situation may further reduce your return.

Platform, sale, rights and technology: A platform failure may delay communications or payments. However, your contractual claims against the project owner remain unaffected. You will generally not be able to terminate the bond early; moreover, there is no liquid secondary market. A sale may be impossible or may result in losses. You have no voting rights, and the bond terms may be amended by the required majority. Technical problems, cyberattacks or loss of access to the digital register or electronic vault may temporarily or permanently prevent access to the bonds.

A complete and detailed description of all risk factors can be found exclusively in the KIIS in the document section of this financing round.


-----End of marketing content-----

Documents

Investment-related documents

Log in to access further information.

Updates

No updates are currently available.

This section will be regularly updated with new, project-relevant information throughout the financing period. To be notified promptly about new updates, subscribe to our newsletter.

Invesdor is a Eurocrowd platform member.

Ausgezeichnet als Top-Innovator 2021

Winner of the Golden Bull as the best
Crowdfunding platform 2023.

ECSP lizensiert

Invesdor is licensed under the
ECSP regulation of the EU.